Polarled Pipeline Project

Garagol Deniz Project
December 1, 2014
1995
March 1, 2015

Polarled Pipeline Project

Project Name Polarled Pipeline Project
Project Owner Statoil Petroleum AS on behalf of owner group
Year of Completion 2015
Scope of Work 492 km of 36” pipes.
3LPE (Linepipe and Buckle Arrestor), 3LPP(Linepipe and Buckle Arrestor), IFC (Internal flow coating), CWC Coating, Marine Logistics, Transshipment of CWC pipes, Anode and Doubler plate supply and Installation.
Project Location Norway (CWC) (Internal and anti-corrosion coating done in Kuantan)

The Polarled-pipeline will export gas from the Aasta Hansteen field in the Norwegian Sea to the Nyhamna gas plant near Molde. No other oil/gas pipeline of this dimension has ever been laid at these water depths before.The total estimated value for the three contracts is 4 billion Norwegian crowns. The contracts have been awarded on behalf of the Polarled partners and are the result of a broadly based, competitive international tender between pre-qualified suppliers.

Want to read more about the project, please contact enquiry.corpcomms@wascoenergy.com